Home MenuBridge Over Brookwood Project
Project Overview
The City of Hillsboro was awarded a $1 million grant from Metro Regional Government to complete preliminary designs on a pedestrian bridge over NE Brookwood Parkway.
A crossing over Brookwood Parkway was identified as a key need in Hillsboro’s 2018 Crescent Park Greenway Concept Plan. The Greenway is a planned 16-mile network of trails, parks, natural areas, and trailheads that will connect neighborhoods along the north, west, and south sides of Hillsboro.
The bridge would safely connect the newly constructed Crescent Park Greenway trail on the west side of NE Brookwood Parkway (south of U.S. Highway 26), to the future trail on the east side (near Top Golf), which will eventually connect to the Gordon Faber Recreation Complex. See a map of the location.
The Crescent Park Greenway Plan was developed with extensive community engagement and is intended to provide safe, accessible connections for people walking, rolling, and bicycling while expanding opportunities to experience nature and recreation.
This phase of the project will define:
- what a crossing would look like
- where it could be placed
- how people will get up and over the bridge
The bridge design process began with six concepts that were evaluated based on technical analysis, cost, environmental considerations, and community feedback. This preliminary phase funded by Metro will conclude with the selection of a preferred bridge alignment and bridge design.
Future phases of the Bridge Over Brookwood Project, including final design and construction, will depend on funding and additional project planning. Updates on next steps will be shared as they become available.
Current Status: Initial Project Phase
After the second project open house and community survey in January 2026, the Crescent Arch and Organic Truss designs were identified as the leading options to move forward.
Provided with these two design options, the Parks & Recreation Commission selected the Crescent Arch design during the May 28 Commission meeting based on strong community support for the design and its favorable construction cost.
To complete this phase of the project, the consultant will now advance the design of the bridge to 30 percent and provide a cost estimate for full construction of the bridge and the approaches leading up to the bridge.